Detail of the construction process of thermal insulation coating
The construction of heat-insulating and cooling coatings is a task that requires rigorous operation. The following is the detailed construction process flow:

Preparation before construction:
1.Base treatment: Ensure that the construction surface is clean, flat, and firm, without defects such as oil stains, dust, loose materials, and cracks. If there are cracks or uneven areas, repair and grinding treatment is required.
2.Environmental conditions: The temperature should be between 5℃ - 35℃, and the relative humidity is less than 85%. Avoid construction under severe weather conditions such as strong wind, rain, and snow.
3.Material preparation: Stir the coating evenly, check the quality and consistency. If necessary, an appropriate amount of diluent can be added for adjustment.
Construction steps:
1.Primer construction (if necessary): For some base surfaces, it may be necessary to first apply a layer of primer to enhance adhesion and seal the base. The primer should be applied evenly without missed areas. The next step can be carried out after the primer is dry.
2.Brush coating: Use a high-quality brush, dip an appropriate amount of coating, and start from one direction and evenly brush it on the construction surface. Keep the angle between the brush and the surface between 45° - 60°. The width of each brushing should not be too large to ensure a uniform coating thickness.
3.Roller coating: Select an appropriate roller, dip it full of coating, and then roll it on the construction surface. Keep a uniform speed when rolling to avoid missed areas and uneven thickness. Roll vertically first and then horizontally to ensure uniform coating coverage.
4.Spray coating: Use a spray gun to evenly spray the coating on the construction surface. Keep the distance between the spray gun and the construction surface between 30 - 50 centimeters. The movement speed of the spray gun should be uniform and the spraying pressure should be moderate.
Construction precautions:
1.During the construction process, maintain the continuity and integrity of the coating to avoid phenomena such as missed coating, accumulation, and sagging.
2.The construction interval between each coating layer should be determined according to the performance of the coating and environmental conditions. Generally, it is 2 to 4 hours to ensure the drying and curing of the previous coating layer.
3.After the construction is completed, clean up the construction site and properly store the remaining paint and tools.
Construction quality inspection:
1.Appearance inspection: The coating should have a flat and smooth surface, uniform color, and no defects such as sagging, blistering, and cracking.
2.Thickness inspection: Use a thickness gauge to check the thickness of the coating, which should meet the design requirements.
3.Adhesion inspection: The adhesion of the coating can be checked by the grid method or the pull-off method and should reach the specified standard.
The above construction process is for reference only. During specific construction, please strictly follow the coating product instructions and relevant construction specifications for operation. If you have any other questions or need further explanations, please visit our website and leave a message at www.santams.com at any time.